Exposé: Central expressway contractor Taisei seeks Rs 4bn compensation from Gov.

The infamous Taisei Corporation of Japan which secured the contract to build phase 3 of the Central Expressway, contravening the accepted tender procedure, is now seeking compensation of 4 billion rupees from the government as a late fee for the Colombo Outer Circular Highway.

The section of the Colombo Outer Circular Highway from Kaduwela to Kadawatha, was built by the Taisei Corporation. There had been a 190-day delay by the Road Development Authority in taking over the road following the completion of construction.

In this letter to the subject minister dated the 4th of June, the Taisei Corporation demands a payment of 4 billion rupees as the estimated prolongation cost. The letter has been signed by Hiroki Horikawa, Chief Representative for the Taisei Corporation in Sri Lanka.

The letter also notes that the Deputy Team Leader in charge of the project had rejected the whole claim for prolongations costs made by the Taisei Corporation. The Taisei Corporation also issues a veiled warning in this letter that if the matter is not resolved, the next available step is to “escalate the matter to the Dispute Adjudication Board and thereafter to arbitration which will not only take time but will also burden the parties to incur substantial costs”.

Horikawa notes that as previously experienced in the Southern Transport Development Project, the impact of arbitration led to the government having to bear a cost of nearly 5 billion rupees. The letter reads, “Ultimately the RDA paid very much more than the claim, the amount of which was colossal”.

Horikawa writes, “We look forward to your kind intervention in this matter and bring about a speedy resolution of the same for mutual benefit” adding that “We shall be free to come over at any time convenient to you for a discussion with your good self”.

The Taisei Corporation also expresses deep concern over the expiration of the JICA loan agreement on the 15th of July 2018 noting that if a resolution of this dispute can be arrived at in a timely manner, the said balance loan can be availed of and the matter could be settled for “mutual benefit”.

Given the troubled past of Taisei Corporation in Japan, the question that comes to mind is who is going to enjoy these mutual benefits and what are these mutual benefits.

AddThis Website Tools
Lankanewspapers

Recent Posts

LNP – 12 spots filled: Who will complete the Miss World 2025 top 40?

The countdown to Miss World 2025 finals has begun as 40 contestants, including fast-track winners…

15 mins ago

LNP – Arugam Bay ‘bikini ban’ work of an organised group

The Defence Ministry and the Inspector General of Police (IGP) have been asked to urgently…

16 hours ago

LNP – Cost of living in Sri Lanka has doubled since 2021 – CBSL

The Central Bank of Sri Lanka (CBSL) states that the cost of living for individuals…

16 hours ago

LNP – SC to hear petitions filed challenging Deshabandu’s appointment as IGP

The Supreme Court today (28) ordered that the petitions filed, seeking a ruling that the…

16 hours ago

LNP – Govt. considers pact termination with over US $ 40 million compensation for fresh deal

The government mulls termination of the current project for the construction of the Kadawatha -…

22 hours ago

LNP – Colombo Stock Exchange records landmark single-day turnover

The Colombo Stock Exchange (CSE) recorded a significant milestone today (27), with its total market…

24 hours ago